Preparation before installation
Pretreatment of coal bunker wall
- Completely remove residual coal slag, rust, cement lumps and other debris in the bunker to avoid impurities causing the lining to not fit properly.
- If there are cracks, protrusions or depressions in the bunker wall, cement mortar or welding should be used to fill them. The protruding parts should be polished to a flat surface to ensure that the gap between the lining and the bunker wall is ≤1mm.
- According to the coal bunker structure, draw horizontal and vertical reference lines on the bunker wall as the positioning basis for the layout of the lining, especially at the feeding port, the slope should be consistent to avoid steps.
Pretreatment of lining
- Cut the lining according to the layout size. It is recommended to use a special saw blade to cut the plate to avoid burrs. Special-shaped parts need to be prefabricated in advance to ensure that they match the curvature of the bunker wall.
- If the liner is curled during storage, it can be laid flat in advance and pressed with heavy objects for 24 hours to reduce the rebound after installation.
Installation principles
Straight wall section installation
Adopt the order of "from bottom to top, from left to right", and the joints of adjacent linings need to be staggered to avoid coal jamming caused by through seams.
Dumping port installation
The dumping port is the area where coal impact is most concentrated. The lining plate needs to be arranged in a trapezoidal shape of "wide at the top and narrow at the bottom", fitting the taper slope, and the joints need to transition smoothly to avoid the formation of steps and coal blockage.
Precautions when installing coal bunker lining
1. During the installation process, the countersunk plane of the bolts of the polymer polyethylene lining plate should be lower than the plate surface.
2. When installing coal bunker lining products, no less than 10 bolts should be used per square meter.
3. The gap between each lining plate should not be greater than 0.5cm. During installation, it should be adjusted appropriately according to the ambient temperature of the plate.
4. After installation, a small amount of coal can be passed in to test the smoothness of the dumping, and observe whether there is coal hanging or blockage. If there is any abnormality, it needs to be adjusted in time.
5. After 1-2 weeks of use, it is necessary to review the tightness of all bolts, especially the dumping port area. Material impact may cause the bolts to loosen. If there is any looseness, they need to be reinforced in time.
If you want to know more about polymer coal bunker lining, you can send us an email. We will have professional technicians to answer your questions! lucy@chinaupe.com


Need help matching this material to your project?
Send your project size, thickness, working environment and expected quantity. OKAY Plastics can help review suitable material options, processing details and quote requirements for industrial use.
Related product pages for quotation review
- UHMWPE coal bin liner for bin drawing, liner thickness, fixing method, quantity and destination review
- UHMWPE silo liner for storage system drawing, material flow and installation layout comparison
- UHMWPE chute liner for transfer point wear area and impact condition reference
- Send coal bin liner drawing, material handled, destination and estimated quantity for quotation